Fictional report example
Example commercial dilapidations condition report
A detailed fictional lease-end inspection showing the type of report PropertySurvey Pro can produce from a fully completed survey.
Fieldstone Building Surveys
Independent commercial building inspections
Commercial Dilapidations Condition Report
Northbridge Estates Ltd
Freeholder
Unit 7 Meridian Court, Stoke-on-Trent, ST4 8EX
Light-industrial unit with ancillary offices · EPC D (potential B)
Lease-end condition and remedial-cost evidence
Company History
Fieldstone Building Surveys is an independent practice providing commercial building inspections, schedules of condition and lease-end property advice. Reports separate observed condition from professional interpretation, identify inspection limitations and direct specialist matters to appropriately qualified advisers.
Fieldstone Building Surveys
Independent commercial building inspections
Legal Disclaimer
This report records a non-destructive visual inspection of the accessible areas described. It is not a structural design, measured survey, services test, valuation or legal opinion on lease liability. Concealed construction was not opened up. The client and its legal advisers must interpret repairing covenants, supersession and any formal claim; specialist testing is required where the report says “Seek Further Advice”.
Client Instructions
Record the accessible condition of Unit 7 before the stated lease end, identify material repair and reinstatement items, relate observations to recorded locations, and provide budget allowances for discussion with the client’s legal and property advisers. Review the warehouse, office pod, welfare areas, envelope, yard and visually accessible services. The signed lease, licences for alteration and full services records were not provided, so covenant liability is outside this instruction.
Executive Summary
Primary defect. Localised water staining below the north-west rooflight aligns with a split rooflight kerb seal and corrosion at the adjoining box-gutter lap. The area was damp at inspection following overnight rain; the remainder of the warehouse roof lining was dry on comparative checks.
Other repairs. The east roller-shutter bottom rail is corroded, one yard slab has a raised edge, and local office ceiling finishes below the rooflight require renewal after the envelope repair and drying period.
Services. Services were observed but not tested. No current electrical inspection record was made available; a competent electrical contractor should review the installation and records. This is a further-advice item, not an assumed repair cost.
Overall position. The unit remained operational and no immediate instability was observed in accessible areas. The rooflight/gutter repair should be prioritised to limit deterioration. Budget allowances total £5,490 excluding VAT, with electrical advice excluded from that total.
Fieldstone Building Surveys
Independent commercial building inspections
Scope & Definitions
Inspection extent
Ground and first-floor accommodation, warehouse floor, accessible elevations and yard were inspected. The roof covering was viewed from ground level, the first-floor window and an internal access platform supplied by the occupier. Stored goods restricted approximately 12% of the north warehouse wall. No destructive opening-up, drainage test or service isolation was undertaken.
Reporting basis
Observations distinguish visible evidence, surveyor interpretation, recommended work and matters requiring specialist advice. Cost entries are budget allowances rather than quotations. The report can support dilapidations discussions but does not determine legal liability.
Technical Definitions
- Observation
- A condition or feature visible within the recorded inspection limits.
- Interpretation
- The surveyor’s evidence-based view, subject to the stated limitations and any further investigation.
- Budget allowance
- An indicative figure for planning; not a tendered price or valuation of a legal claim.
- Seek Further Advice
- Obtain advice from an appropriately qualified person before the scope or cost of work is determined; no allowance is included until that advice is received.
Energy Performance (EPC)
Property type: industrial unit with ancillary offices. Recommendation: review lighting controls and roof insulation when planned envelope work is scoped. The EPC provides energy context; it does not establish the cause or liability for any defect.
Fieldstone Building Surveys
Independent commercial building inspections
Description of Property
Detached light-industrial unit constructed circa 1997. Steel portal frame with insulated composite wall and roof cladding above a masonry plinth, translucent rooflights, internal box gutters and a two-storey masonry/blockwork office pod. The site includes a surfaced service yard, palisade boundary fencing and marked parking. Approximate gross internal floor area from the supplied EPC is 742 m².
External Observations
- Split sealant and slight kerb separation at the north-west rooflight; corrosion and staining at the adjacent box-gutter lap.
- East roller-shutter bottom rail locally corroded, with coating loss but no visible distortion of the guides.
- One concrete yard slab edge raised by approximately 18 mm on the pedestrian route beside the loading door.
- Wall cladding, masonry plinth and rainwater downpipes otherwise appeared generally serviceable from accessible viewpoints.
Internal Observations
- Localised brown staining and softened ceiling tile directly below the north-west rooflight/gutter junction.
- Comparative pinless moisture readings reduced away from the affected area; no similar staining was found at other rooflights.
- Office, welfare and warehouse finishes were generally serviceable, with ordinary wear consistent with use.
- A fine vertical finish crack at the office stair enclosure measured 0.5 mm and showed no associated distortion.
Services Assessment
Electrical distribution, gas-fired unit heaters, hot-water point, fire-alarm components and above-ground drainage were viewed where accessible but were not operated, isolated or tested. The occupier supplied a fire-alarm service sheet dated February 2026. No current electrical inspection report was presented. Condition, safety and statutory compliance must be confirmed from records and by appropriately qualified contractors.
Methodology
Visual inspection supported by laser distance measurements, a crack-width gauge and comparative non-invasive moisture readings. Roof areas were viewed only from the positions stated in the scope. No drone, pole-camera survey, thermal-imaging survey or laboratory analysis was undertaken.
Fieldstone Building Surveys
Independent commercial building inspections
Floor Plan
Diagrammatic plan · not to scale · use for inspection-location reference only
Weather & Property Orientation — North-West
Approximately 6 mm of rain was recorded overnight before the inspection. The north-west roof slope and box gutter are comparatively exposed to prevailing weather. Weather data provides inspection context and does not, by itself, establish defect causation.
Fieldstone Building Surveys
Independent commercial building inspections
Subsoil & Drainage Details
| Dataset field | Recorded result | Use in this report |
|---|---|---|
| Modelled soil type | Loam with clay influence | Desk-based site context only |
| Clay / sand / silt | 31% / 36% / 33% | Not a site sample or foundation investigation |
| Drainage characteristic | Moderate | Does not confirm below-ground drainage condition |
| Observed surface drainage | Yard gullies clear at inspection | Visual observation; drains not tested |
No conclusion about structural movement or drainage capacity is drawn from the modelled soil dataset. The observed rooflight/gutter defect provides direct evidence for the local internal staining.
On-site Assessments
Floor Area Measurement (RICS basis)
684.0 m² NIA · 7,363 sq ft
| Basis | Measured areas | Deductions |
|---|---|---|
| Net Internal Area (NIA) — RICS Code of Measuring Practice | Warehouse 472 m² · ground-floor offices 86 m² · welfare 32 m² · first-floor offices 112 m² · gross entered 702 m² | Stair, plant and circulation 18 m² · net result 684.0 m² |
Dimensions entered on site; a calculation aid, not a measured survey. The EPC gross floor area uses a different basis and is not expected to equal NIA.
Crack Damage Category (BRE Digest 251)
Category 1 — Very slight
| Crack width | Pattern | Location | Corroborating signs |
|---|---|---|---|
| 0.5 mm · up to about 1 mm | Vertical, fairly uniform width | Office stair enclosure finish | No sticking doors, frame distortion or multiple related cracks |
Record and re-inspect during planned decoration. Escalate for further assessment if the crack widens, recurs quickly or develops associated displacement or distortion.
Fieldstone Building Surveys
Independent commercial building inspections
External Analysis
Rooflights and box gutter — north-west roof slope
Priority repair- Observation
- Sealant was split at the rooflight kerb and the adjoining box-gutter lap showed coating loss, corrosion and a damp debris line.
- Linked evidence
- Local internal staining and elevated comparative moisture were directly below this junction after overnight rain.
- Recommendation
- Have a competent roofing contractor open, clean and repair the kerb and gutter joint, check adjacent laps and outlets, then water-test and photograph completion.
- Follow-up
- Allow the internal area to dry and confirm stable readings before ceiling finishes are renewed.
Roller-shutter bottom rail
Remove loose corrosion, assess remaining section, repair locally where viable and reinstate a compatible protective coating. Confirm smooth operation after work.
Raised yard slab edge
Make the pedestrian route safe, then lift/re-bed or locally reconstruct the affected slab while maintaining falls to the yard drainage.
External Inspection Record
Roof viewing position recorded
Rooflight and gutter location linked
Wall cladding inspected visually
Rainwater outlets viewed
Yard route inspected
Roller shutter viewed externally
Fieldstone Building Surveys
Independent commercial building inspections
Internal Room Findings
Warehouse — north-west bay
Below rooflight R4 / box-gutter junction
Observations
Local brown staining, a softened ceiling tile and elevated comparative reading aligned beneath the rooflight/gutter defect. Adjacent bays were dry on the same comparative check.
Recommendations
Complete the external repair and water test, allow drying, then replace the damaged tile and redecorate the local area. Reinvestigate if moisture persists.
Office stair enclosure
Ground-to-first-floor wall finish
Observations
Fine isolated crack in the decorated finish. Doors operated normally and no frame distortion, displacement or matching external crack was found.
Recommendations
Fill and redecorate during planned works; retain a dated record and review if it widens or associated movement appears.
Offices and welfare areas
Accessible ground and first-floor rooms
Finishes showed ordinary wear. No material water staining, distortion or unsafe floor transition was observed in the accessible rooms. Services comments remain subject to the separate visual-only limitation.
Fieldstone Building Surveys
Independent commercial building inspections
Essential Summary of Costs
Independent Surveyor Disclosure
Fieldstone Building Surveys and the surveyor have no financial interest in any contractor who may undertake the works. The amounts are budget allowances for client planning, not quotations, tendered prices or an assessment of lease liability. Scope and access can materially change final cost.
| Description | Status | Cost |
|---|---|---|
| Repair rooflight kerb and box-gutter lap; check adjacent joints and water-test | Standard | £2,850.00 |
| Prepare and repair roller-shutter bottom rail; reinstate protective coating | Standard | £760.00 |
| Make safe and re-bed/reconstruct raised yard slab edge | Standard | £1,200.00 |
| Replace local ceiling tile and redecorate after confirmed drying | Standard | £680.00 |
| Review electrical installation records and advise on testing/remedial scope | Seek Further Advice | — |
Subtotal: £5,490.00
VAT (20%): £1,098.00
Total: £6,588.00
Cost Review Notes
- Obtain competitive quotations against a defined repair specification.
- Confirm safe roof access, edge protection and disposal requirements with tenderers.
- Keep electrical testing and resulting remedial work outside the allowance until a competent contractor has defined the scope.
- Legal advisers should assess covenant liability and whether any item is superseded by the client’s intended works.
Fieldstone Building Surveys
Independent commercial building inspections
Important Notes
- This report describes accessible condition on 28 July 2026; it does not guarantee concealed areas are defect-free.
- Repair the rooflight/gutter defect before renewing internal finishes, then verify drying and water-tightness.
- Services were not tested. Obtain and review relevant records and commission specialist advice where records are absent or concerns arise.
- Budget allowances are not contractor quotations and exclude professional fees, access design, disruption, statutory fees and unforeseen work unless expressly stated.
- The report supports evidence gathering. Lease interpretation, formal notices, quantified demands and negotiations remain matters for appropriately appointed professional and legal advisers.
Declaration
I confirm that this report records the observations, limitations, interpretations and recommendations stated. I have reviewed the relationship between the roof defect and internal evidence, separated visible condition from legal liability, and identified where specialist advice is required.
The report has been checked for internal consistency. Costs are budget allowances for planning and are not contractor quotations or an assessment of lease liability.
Survey prepared and signed by
Maya Bennett
Maya Bennett MRICS
Signed: 30 July 2026 · Reference FBS-2026-0728